Dry Docking


Date:
16/06/2006
Project Title:
Dry-docking of P/V Salamis
Client:
Cyprus Navy
Vessel:
P/V SALAMIS
Description:

Multimarine was contracted by the Cyprus Navy to lift out of the water and carry out complete maintenance of hull and repair of the Propulsion System of the P/V Salamis. Phase 1 of the project consisted of the design and fabrication of a Special Steel Cradle. Phase 2 consisted of lifting out of the water and placing the vessel on the cradle. Phase 3 consisted of  untertaking and performing complete maintenance of hull including wood treatment and coating, and the survey and repair of the propulsion system (shafts, bearings, propellers, rudders etc). On completion the vessel was placed back in water.