Description:

Multimarine completed a 3 day demobilisation works on board Normand Cutter. 

During the scope of the demobilisation, Multimarine provided a strong team comprised of a project manager, foremen, burners, general assistants, fire watchers, joiners, electricians, riggers and Gas Free technicians. In addition, Multimarine provided a mobile Crane 250Te, flat bed trucks, low loaders, 3 forklift trucks (5te, 10te and 20te) and a 250KVA generator. 

The scope of work included the burning of all seafastening plates, offloading all equipment and transfer to the storage area, and reinstatement of deck and bulwark.